Announced isn't built.
See which US datacenter megawatts are real before they reach your model. Every stage and figure links to the filing behind it.
In private build, Texas first. One email when your access opens.
Each project counted at its current stage.
- AnnouncedPress reports
- FiledPUCT 58881
- Approved, cond.Order 105 · 2026-04-23
- Under constructionNo record yet
- EnergizedNo record yet
Proven
- Net metering approved
- Customer is Ensign, not Crusoe
- Compliance tracked in Docket 59616
Not proven yet
- Construction start
- Energization date
Condition Curtail within 30 min on ERCOT instruction in an emergency
For your modelCount 265 MW as approved load, not built
04-232026
ArmstrongStage change
Filed→Approved, conditional
PUCT 58881 · Order 105
Model impact265 MW moves to approved. Still not built.
03-092026
Lancium AbileneNew document
Incentive report filed: 57 new jobs a year, listed for 10 years.
TX Comptroller Ch. 312 · 000017851
Model impactNo MW change
12-022025
Vantage TX2 / TX21New documentConflict
Draft air permit: 65 diesel backup engines.
5207 Rogers Rd (TCEQ) ≠ 5702 Rodgers Rd (site plan)
TCEQ draft · 2025-12-02
Model impactNo MW change. Site count under review.
Armstrong,"Armstrong County, TX",Approved,180+85,PUCT 58881,2026-04-23
{ "project": "Armstrong", "stage": "Approved",
"mw": [180, 85],
"source": { "doc": "PUCT 58881", "date": "2026-04-23" } }Excel, CSV or API. Every row keeps its receipt.
180 + 85 MW · PUCT 58881 · 2026-04-23
— MW · TX Comptroller 312
16 MW fit-out · TCEQ draft · 2025-12-02
- AnnouncedPress reports
- FiledPUCT 58881
- Approved, cond.Order 105 · 2026-04-23
- Under constructionNo record yet
- EnergizedNo record yet
Proven
- Net metering approved
- Customer is Ensign, not Crusoe
- Compliance tracked in Docket 59616
Not proven yet
- Construction start
- Energization date
Condition Curtail within 30 min on ERCOT instruction in an emergency
For your modelCount 265 MW as approved load, not built
04-232026
ArmstrongStage change
Filed→Approved, conditional
PUCT 58881 · Order 105
Model impact265 MW moves to approved. Still not built.
03-092026
Lancium AbileneNew document
Incentive report filed: 57 new jobs a year, listed for 10 years.
TX Comptroller Ch. 312 · 000017851
Model impactNo MW change
12-022025
Vantage TX2 / TX21New documentConflict
Draft air permit: 65 diesel backup engines.
5207 Rogers Rd (TCEQ) ≠ 5702 Rodgers Rd (site plan)
TCEQ draft · 2025-12-02
Model impactNo MW change. Site count under review.
Armstrong,"Armstrong County, TX",Approved,180+85,PUCT 58881,2026-04-23
{ "project": "Armstrong", "stage": "Approved",
"mw": [180, 85],
"source": { "doc": "PUCT 58881", "date": "2026-04-23" } }Excel, CSV or API. Every row keeps its receipt.
Headline megawatts don't survive the filings.
Three misreads from public records. Each one changes a model.Three misreads from public records.
Read as site load
265.5 MW
Read as site load, but: Wind generation, not load
PUCT 58881 · Order 105
Summed as new jobs
570 jobs
Summed as new jobs, but: 57 a year, listed 10 times
TX Comptroller · Ch. 312
Counted as two sites
5207 ≠ 5702
Counted as two sites, but: Two addresses, one site
TCEQ draft · TDLR site plan
Built for a number you can defend
For analysts who answer to a PM or an investment committee.
Every figure has a source
Click any MW, stage or party. See the filing, page and date.
- Agency
- PUCT · 58881
- Pages
- 2–3, 19–21
- Signed
- 2026-04-23
Conflicts flagged, not averaged
When two filings disagree, you see both.
Into your model, sources attached
Excel, CSV or API. Every row keeps its receipt.
Armstrong,"Armstrong County, TX",Approved,180+85,PUCT 58881,2026-04-23
{ "project": "Armstrong", "stage": "Approved",
"mw": [180, 85],
"source": { "doc": "PUCT 58881", "date": "2026-04-23" } }Notes from the filings
How to read the public record behind a datacenter.
Announced isn't built: reading a datacenter's stage from the record
Five stages, the document that proves each one, and where it usually lives.
Data center megawatts: IT load vs utility load
A data center MW figure can mean IT load, grid capacity requested or generation. How to tell which one a filing reports before you model it.
How long it takes to build a data center, by stage
Build time for a data center, stage by stage, from filing to energization. Each range is tied to the document that starts or stops the clock.